Summary
USDA's $5 billion guarantee is sized for regional packers, lends into the bottom of the cattle cycle, and makes a third-party feasibility study mandatory on every file. This is what the primary text says, and what the last program taught.
32 minute read.
USDA's $5 billion guarantee is sized for regional packers, lends into the bottom of the cattle cycle, and makes a third-party feasibility study mandatory on every file. This is what the primary text says, and what the last program taught.
Summary
On October 23, 2026, USDA Rural Development opened the Strengthening Processing for U.S. Ranchers (SPUR) Guaranteed Loan Program: at least $5 billion in loan level, a 90 percent guarantee, a $175 million aggregate cap per borrower group, and an expected 50 to 100 awards (1). That last pair of numbers is the first finding of this piece. Fifty to one hundred awards from $5 billion is an average loan of $50 million to $100 million. Twenty-nine loans at the cap would exhaust the authority. USDA's most recent small-processor grant round, announced three days later, averaged about $390,000 per award (31). SPUR is a regional-packer program carrying a small-processor label.
The second finding is timing. There were 27.6 million beef cows in the United States on January 1, 2026, down 1 percent, and the 2025 calf crop was the smallest in decades (24). Commercial cattle slaughter fell 6 percent in 2025, and USDA's own outlook has 2027 beef production falling again (25, 44). Beef packer margins swung from roughly negative $311 a head in late July 2026 to positive $54 in late October (26). The largest packer removed more than 10,000 head a day of capacity in 2026 and the industry still runs near 78 percent utilization (27, 45). A plant underwritten in 2027 opens into that market, not the one described in the press release.
The third finding is history. SPUR's direct predecessor, the Food Supply Chain Guaranteed Loan Program, ran on the same statutory authority with a $40 million cap. USDA's last public list shows about $507 million closed against roughly $1 billion offered (13, 14). Only about eleven of those loans went to meat, poultry or seafood plants, and the largest poultry loan failed seventeen months after it closed (19, 20). USDA's Inspector General questioned every dollar of the first $208 million in companion grants (16).
The fourth finding is the gate. NOFO §5.2(b)(vii) requires a feasibility study by a qualified consultant in every full application, with twenty-one enumerated elements, including animal supply, water and waste, worker and food safety plans, contracts, and a quantified capacity claim (1). The Business and Industry program requires one only above $1 million for a new business (5). The program's hardest requirement is not equity. It is the study. Written for lenders, loan committees, processors, and the investors behind them. 32 minute read.
Key figures
| Figure | Value | Source | As of |
|---|---|---|---|
| Program level | At least $5 billion in guaranteed loans | SPUR NOFO §3.0; 91 FR 67540 | October 23 to 27, 2026 |
| Cap per borrower group | $175 million, aggregate, including dependent affiliates | SPUR NOFO §3.0(a) | October 23, 2026 |
| Guarantee and retention | 90 percent guarantee; lender holds 10 percent | SPUR NOFO §3.0(b), §6.1(e) | October 23, 2026 |
| Expected awards | 50 to 100, implying $50 million to $100 million each | SPUR NOFO §3.0 | October 23, 2026 |
| Beef cow herd | 27.6 million head, down 1 percent | USDA NASS, Cattle | January 1, 2026 |
| Predecessor program closed | About $507 million of roughly $1 billion offered | USDA FSC awards list | November 14, 2023 |
The guarantee covers the lender's loss. It does not fill a kill floor, and the application knows it.
By Michal Mohelsky, J.D., FMVA. MMCG Invest, LLC. Published November 2, 2026. Current as of November 2, 2026.
The sentence circulating in lender decks since October 23 reads roughly like this: USDA has put $5 billion behind small, independent meat processors, with a 90 percent guarantee, no geographic restrictions, loans up to $175 million, and two years before anyone has to make a payment. Every clause in that sentence can be traced to a USDA document. The conclusion most people draw from it, that a wave of small-plant financing is about to begin, cannot.
The numbers are right. The program they describe is not small. Fifty to one hundred awards from $5 billion is a program of regional packers, non-dominant integrators, and seafood companies large enough to use a nine-figure loan. The "two years" is a deferral under which interest accrues and the first annual interest payment is due within twenty-four months. "No geographic restrictions" removes exactly one test from the Business and Industry rulebook, the rural one, and leaves every other test in place. And the $175 million is not a loan size. It is an aggregate ceiling on a borrower and everything that depends on it.
We have spent the last ten days reading the primary text: the 19-page Notice of Funding Opportunity, the Federal Register notice, the program page and FAQ, 7 CFR Part 5001, and the record of the programs that came before it (1, 2, 3, 5). We also went back through the credit files we know from the last cycle of independent-plant financing, including the ones that did not end well. The thesis that emerged is simple. SPUR will be won or lost on the feasibility study, because the NOFO makes the study mandatory in every full application, because the study is where animal supply, utilization, wastewater and management depth get tested, and because those four things, not the plant itself, are where independent processors have historically died.
This piece covers what the program is and is not, the arithmetic that sets its real audience, what happened the last time USDA used this authority, the market a 2027 plant will open into, the plant-level economics a reviewer will test, how a lender will structure the credit, and what the study has to contain. It closes with what we would do differently if we were building the file today.
Two programs, one acronym
Before anything else, a disambiguation, because half of the confusion we have seen in October traces to it. USDA launched two programs this year under the name Strengthening Processing for U.S. Ranchers.
The first, announced June 30, 2026, is a payment program. It is run by the Farm Service Agency under the Commodity Credit Corporation Charter Act, it pays up to $500 million in temporary per-head support to beef slaughter plants that are domestically owned and not nationally dominant, and its application window closed September 30, 2026 (9, 10). It is cash, it is beef only, and it is over.
The second, announced October 23, 2026, is the loan guarantee program this piece is about. It is run by the Rural Business-Cooperative Service under Section 1001(b)(4) of the American Rescue Plan Act and administered under the OneRD rule at 7 CFR Part 5001 (1, 2, 6). It covers meat, poultry and seafood. USDA's own September 4 release called it "SPUR 2.0" (11). Nothing in either primary text links the two. A plant that received June payments has no priority in the loan program, the $500 million is not part of the $5 billion, and a lender who underwrites the payments as a credit enhancement is underwriting something that does not exist.
The loan program's policy lineage matters for one reason. Executive Order 14424 of September 4, 2026 directed a guaranteed loan program "for small and regional beef processors" (11). The NOFO that implemented it is far wider: all amenable meat species, poultry including egg products, seafood, and partners of processors such as feedlots, renderers and pet-food plants, with a $175 million ceiling (1). The executive order describes the politics. The NOFO describes the program. Read the second.
The rulebook: what SPUR actually is
SPUR is a B&I loan with six amendments. The NOFO says so in nearly those words: the program is "designed and implemented in a manner similar to the Business and Industry (B&I) Guaranteed loan program with minor changes," and guaranteed loans "are administered under 7 CFR part 5001… as amended or supplemented by this Notice" (1). Everything the NOFO does not touch defaults to the OneRD rule. That default is the most important sentence in the program, because the OneRD rule is where equity, collateral, appraisal, construction monitoring and loss-claim reduction all live (5).
The six changes are these. First, the rural-area test is gone; projects "may be located in any rural or non-rural area of a State" (1). Second, the guarantee is 90 percent, against 80 to 85 percent for B&I this year (2, 3). Third, the lender must hold at least 10 percent of the total loan, overriding the 7.5 percent in §5001.408 (1, 5). Fourth, the cap is $175 million, measured against the borrower together with "affiliate entities dependent upon another's operations and generation of revenue for loan repayment," counting both the guaranteed and unguaranteed portions and any outstanding SPUR balance (1). Fifth, the deferral: "subject to lender and Agency approval, SPUR loans may allow for a two-year deferral of principal and interest payments," with interest due at least annually starting no later than two years from the note and the first full principal and interest payment no later than three years (1). Under the base rule, interest starts within one year; SPUR moves that to two and leaves the three-year amortization start alone (5). Sixth, new eligibility screens: domestic ownership with a majority of U.S.-citizen owners, independent ownership, an FSIS, Cooperative Interstate Shipment or equal-to-federal state inspection certificate in place by the time the loan note guarantee issues, a bar on foreign-adversary ownership, and the market-share test (1).
The market-share test deserves its own paragraph because it is the one rule most likely to be misread. A borrower is ineligible if it, an affiliate, or a toll-processing partner "holds a market share greater than or equal to the entity that holds the fourth largest share of the market, based on verifiable industry or USDA-NASS data for beef, pork, chicken, or turkey processing" (1). Three things follow. The test is species by species, so a firm is screened for the species it is financing. It removes the top four, not the top four plus everyone near them: in chicken that is Tyson, Pilgrim's, Wayne-Sanderson and Mountaire on WATT's 2025 volumes, and Perdue sits roughly 2.5 million pounds a week below the line (42). And the test does not apply to seafood at all, which is why a large domestic seafood processor can borrow at the full cap with no dominance screen (1). The NOFO never says which metric to use, head, weight, capacity or sales. It will be decided on the data the borrower submits, and the feasibility study is where the NOFO asks for it.
The fees are the B&I fees. For FY2027 the Federal Register notice sets a 3 percent guarantee fee on the guaranteed portion, a 0.55 percent annual retention fee, and an additional 0.5 percent if the loan note guarantee issues before construction is complete (2). At the cap, that is $4.725 million up front on a $157.5 million guaranteed balance, about $5.5 million if the guarantee issues pre-completion, and roughly $866,000 in the first year of retention fees. Terms run to the useful life of the collateral, with 40 years as a ceiling under §5001.402, not an entitlement (3, 5). Rates are negotiated, fixed or variable, and the Agency reviews them (3).
Two things the NOFO does not say are worth as much as what it does. It is silent on equity, which means §5001.105(d) applies by default: at least 10 percent tangible balance-sheet equity for an existing business, 20 percent for most new businesses, and 25 percent for a new business seeking the guarantee before construction is complete (5). Marketing that implies "no equity required" is not reading the rule. And the program page still carries the phrase "Pending Congressionally approved funds" while the NOFO says "at least $5 Billion will be available beginning in FY 2027" (1, 3). Both cannot be operative. The NOFO cites the ARPA §1001(a) appropriation; Congress rescinded $1 billion of those unobligated balances in 2022 and, in Section 9 of the Fiscal Responsibility Act of 2023, the remaining unobligated balances as of June 3, 2023, a rescission USDA's own apportionment footnotes acknowledge (6, 7, 8). We cannot reconcile the funding source from the public record, and until USDA does so in writing, a conditional commitment should be treated as subject to availability of funds.
Arithmetic before credit
The NOFO's own numbers set the audience. "At least $5 Billion." "Approximate Number of Awards: 50 to 100." "Maximum Award Amount… $175 million" (1). Divide the first by the second and the average SPUR loan is $50 million to $100 million. Divide the first by the third and 28.6 loans at the cap exhaust the authority. Neither of those is a small-plant number.
Compare it with what USDA actually gives small plants. Three days after the NOFO, the Meat and Poultry Processing Expansion Program announced $57.4 million in tentative awards to 147 projects in 40 states, pending congressional allotment (31). That is about $390,000 each. The implied SPUR average is 125 to 250 times larger. The predecessor loan program capped a borrower at $40 million (13); SPUR's implied average is above the old maximum.
Now compare it with what plants cost. The four regional beef projects of this cycle that have published budgets ran between roughly $207,000 and $333,000 of capital per head of daily capacity: Producer Owned Beef in Amarillo at about $620 million to $670 million for 3,000 head a day, Cattlemen's Heritage in Iowa at $520 million for 2,000, Sustainable Beef in North Platte at about $400 million for 1,500, and America's Heartland Packing in Missouri at $800 million for 2,400 (32, 33). At those rates a 400-head-a-day plant is a $90 million to $130 million project. USDA's October 29 announcement of a B&I guarantee for a 400-head plant in Dimmitt, Texas, put the guaranteed loan at "more than $24 million," which implies either heavy producer equity or a leaner scope than the regional benchmarks (41). Either way, a mid-scale plant is a $25 million to $75 million borrower and a regional one is a cap borrower.
The eligible universe is wide and the fundable universe is narrow. FSIS counted 2,961 very small, 2,847 small and 508 large inspected establishments in December 2025 (30). Nearly all of the first two groups are eligible on paper. Almost none of them needs, or could service, a loan in SPUR's implied range. A very small plant borrowing $2 million would pay the same 3 percent fee, commission the same third-party study, and clear the same OneRD underwriting as a $150 million packer. The program does not exclude them. Its economics do.
Who is left is a few dozen names. Greenfield and expansion red-meat plants of 400 to 3,000 head a day; the handful of broiler and turkey integrators that sit at number five through ten in their species; pork firms below Tyson and the number-four packer, since Smithfield and JBS already fail the domestic-ownership test; brownfield acquisitions of idled capacity, of which Tyson's Pasco, Washington plant is the obvious example (27); and seafood processors, who face no dominance test at all. Our own sizing, with the usual caveat that it is an estimate, puts plausible demand at roughly 95 to 230 loans and $2.3 to $8.4 billion, with 70 to 80 percent of the dollars going to fewer than 50 borrowers. The $5 billion is a reasonable midpoint. It will be absorbed by the top three bands, and the window is first come, first served until the funds run out (1). Projects with permits, offtake and a finished study have a timing advantage that a program with no application deadline makes permanent.
What happened last time
USDA has used this authority before. The Food Supply Chain Guaranteed Loan Program opened on December 9, 2021 under the same ARPA §1001 language, administered like B&I, with a $40 million aggregate cap and a 90 percent guarantee limited to fixed-rate loans priced within prime plus 200 basis points (13). The Federal Register notice offered "approximately $1,000,000,000 in loan guarantees" (13). USDA's last public award list, dated November 14, 2023, sums to about $507 million across 35 line items, an average of roughly $14.5 million (14). Add the loans that appear on later RD lists and the figure may reach about $670 million; an advocacy group claimed about $800 million. No USDA close-out total was ever published. What ended the program was not demand. It was the Fiscal Responsibility Act of 2023, which rescinded the unobligated balances (7).
The meat, poultry and seafood share of that program was small. On our reading of USDA's November 2023 list, about eleven loans and roughly $153 million went to protein processors, under a third of listed dollars; the rest financed dairy, produce, bakery, sweeteners and cold storage (14). Two of those eleven loans are instructive.
Pure Prairie Poultry in Charles City, Iowa, received a $38.72 million guaranteed loan and a $6.96 million MPPEP grant, announced October 21, 2022, to restart a plant that had closed in 2019 and had been the site of several prior failures (18). The loan was executed in April 2023. The chief financial officer's affidavit, as reported by DTN, put operating losses at approximately $38 million from November 2023 through September 2024 (19). The company filed Chapter 11 on September 20, 2024, had the case dismissed a week later, shut the plant on October 2, and left as many as 50 growers unpaid and more than a million birds without feed (19). The lender, Community Bank & Trust, held a claim of roughly $36 million and took the plant with a $25.7 million credit bid approved May 30, 2025 (20). That single loan was about a quarter of the program's protein dollars. In May 2026 USDA revoked the approved-lender status of ten lenders holding about $620 million of delinquent loans, roughly 47 percent of Rural Development's delinquencies; Community Bank & Trust-West Georgia was on the list (21).
Northline Seafoods received the program's $40 million cap for a first-of-its-kind salmon freezer barge in Bristol Bay. A 2024 fire, about $2.8 million of contractor liens and a court-ordered arrest of the vessel in 2025 followed; it posted bond, settled, and operated the 2025 season. It is a live credit under strain, not a loss, and it is a reminder that novel processing assets carry construction risk the guarantee does not cover.
The companion grant program fared no better under audit. MPPEP made 74 awards totaling more than $325 million through September 2024, with USDA reporting funded capacity of 800,000 cattle a year, of which one plant, America's Heartland Packing, accounts for 624,000 (15). The Inspector General's March 2024 audit found that the Rural Business-Cooperative Service "did not develop, document, and implement an effective internal control system" over first-round awards (17). Its December 2024 inspection questioned all $208,285,667 of first-round spending and found that 14 of 20 required onsite reviews were never performed (16). A bipartisan letter of October 25, 2024 noted that USDA had "provided $223 million in loan guarantees and grants to 30 meat and poultry processing companies" over the prior two years and asked whether other lenders had defaulted (18). No public answer has surfaced.
Two lessons carry forward. The projects that succeeded, Sustainable Beef with Walmart as an offtaker and producers as owners, America's Heartland Packing with an $800 million parent behind a $10 million grant, had sponsors and supply before they had federal money (32, 33). The ones that failed were restarts and first-of-kind assets with thin liquidity. And the historical loss profile of B&I itself is reassuring only in aggregate: about $501.6 million of loss payments on $13.4 billion of core obligations from FY2015 to FY2024, averaging just under $30 million a year in the recent period (22). A program with a $175 million cap and a 90 percent guarantee can produce a single loss larger than five of those years combined. SPUR's default count will look fine. Watch the dollars.
The market a plant will open into
A beef plant financed in 2027 will take its first cattle in 2029 or 2030 if it is greenfield, and in 2027 or 2028 if it is a brownfield restart. Either way it arrives near the bottom of the cattle cycle, competing for a shrinking supply against incumbents who are closing plants rather than bidding less.
The herd first. On January 1, 2026, NASS counted 86.2 million cattle and calves, down 0.4 percent, and 27.6 million beef cows, down 1 percent; the 2025 calf crop was 32.9 million, down 2 percent, and cattle on feed were 13.8 million, down 3 percent (24). Beef replacement heifers rose 1 percent, the first retention signal since 2021, and it is too small to change fed-cattle supply before 2028. Commercial cattle slaughter in 2025 was 29.8 million head, down 6 percent, and 937 plants killed at least one animal, with the 11 largest accounting for 47 percent of the total (44). USDA's October outlook has 2027 beef production at 24.675 billion pounds, down another half percent, with slaughter steers forecast at $237.50 per hundredweight for 2027 against $221.05 in September 2026 (25). The raw material does not get cheaper in a new plant's first operating year.
Margins second. AMS publishes the cutout and the cattle price but not packer margins, so the series are private and they disagree, but the range is the point. Sterling Marketing's profit tracker ran from negative $311 a head in late July 2026 to positive $155 in the third week of October and $54 in the fourth, when the comprehensive cutout slipped to $371.93 (26). Terrain put third-quarter margins at negative $200 to $300 a head. Tyson guided to a $500 million to $650 million operating loss in its beef segment for fiscal 2026. A plant underwritten on a normal positive spread will miss its coverage in some quarters of its first three years. That is not a stress case. It is the base case for 2024 through 2026.
Capacity third, and this is the part most pitch decks get backwards. The industry is overbuilt relative to cattle, not short of hooks. Tyson closed Lexington, Nebraska in January 2026 and cut Amarillo to one shift, removing about 7,700 head a day by trade estimates; in August it announced the closure of Joslin, Illinois, about 3,100 head a day, and put Pasco, Washington up for sale (27). Kansas State's Glynn Tonsor said plainly that "the packing sector has too much physical capacity" (27). Fed-plant utilization is running around 78 percent, and Terrain estimates capacity still exceeds cattle availability by 6,000 to 8,000 head a day (45, 46). The four largest packers handled 82 percent of steer and heifer slaughter in 2024, back up from the 81 percent trough of 2020 and 2021 (28). Five years of new independent construction, by one university count, roughly equals one Tyson closure. An independent plant does not enter an underserved market. It enters a market where the dominant firms can reallocate kills across fewer plants and bid for cattle at a loss longer than a new entrant can.
The other species are different problems, not easier ones. Pork is a demand story: the September 1, 2026 hog inventory was down 2 percent, processor spreads were below 2025 levels in seven of nine months, and ERS describes demand "in retreat" at home and abroad (25). Chicken has the best volume backdrop, with 2026 production up 3.4 percent, but integrators own the birds, so an independent SPUR borrower is a further processor or a specialty plant whose grower contracts are the whole credit. Turkey lost a second straight year to avian influenza and metapneumovirus, and USDA's long-run baseline projects it as the only major animal protein not to set a record through 2035 (25). Seafood is where the program is most open and the record least encouraging. NOAA estimates 82 percent of the seafood Americans ate in 2024 was imported, by edible weight, and part of that is American fish processed abroad and reimported (29). Alaska's 2023 to 2026 consolidation, with Trident selling four plants and Peter Pan ceasing operations, says that remote processing capacity is not the binding constraint. Fish volume, global price and fixed cost are.
Two live operating risks round this out. New World screwworm reached the United States in June 2026 and U.S. wildlife in October; Mexican feeder imports are flowing through three ports under conditional protocols, and ERS's planning assumption is that only two remain open through 2027 (25). A Southern Plains plant should underwrite no Mexican volume beyond that. And avian influenza has removed turkey flocks in consecutive years, which is a business-interruption question a lender should ask before closing.
Where plants die
Independent processors rarely fail because the plant does not work. They fail because they cannot keep it full while paying for animals, ramp-up losses and thin spreads at the same time. The guarantee lowers the lender's loss severity. It does nothing to make that happen less often.
Start with what the asset costs and how long it takes. Regional greenfield beef capacity in this cycle cost roughly $207,000 to $333,000 per head of daily capacity and about $730 to $1,000 per square foot all in (32, 33). Construction costs are still rising 4.45 percent a year on the RLB index as of July 2026, with quarterly escalation at a two-year high (40). Concept to first kill ran 36 to 72 months for the four regional plants with public timelines; Sustainable Beef needed 18 public hearings and seven agencies, and America's Heartland built a $140 million wastewater plant, about 17 percent of its budget, before it could open. The grant of inspection is rarely the critical path. Permits, wastewater and the neighbors are.
Then the ramp. Sustainable Beef took its first cattle on May 28, 2025 at about 160 head a day and reached its 1,500-head design in February 2026, eight to nine months later and about six weeks behind plan (32). America's Heartland was at about 800 head a day five months after opening, a third of design, and ran only non-fed cattle for its first year (33). A reasonable single-shift base case is 45 to 60 percent average utilization in year one, 80 to 90 percent in year two, and design in year three, provided supply is contracted. SPUR's deferral allows up to two years without a payment; a lender who matches the deferral to that ramp rather than to the construction period is using it correctly.
Then the fixed-cost arithmetic. Take a $400 million plant financed 60 percent with debt at 7 percent over 25 years. Annual debt service is about $20.6 million, which is about $55 a head at full single-shift throughput and $78 a head at 70 percent. Breakeven for fixed slaughter plants sits around 65 to 80 percent of rated capacity on the studies we have seen, and a 30-point utilization shortfall consumes roughly a sixth of a fed steer's byproduct value in fixed charges alone. Which brings up the byproduct problem. The butt-branded steer hide was worth $95.75 in April 2015 and about $19 to $21 in the autumn of 2025; the branded cow hide was $4.88 on October 23, 2026 (34). The drop credit that used to cushion the spread between cutout and live cost has fallen from roughly 9 percent of live value to about 5 percent, and very small plants now pay $25 to $50 a head to have offal taken away rather than being paid for it.
Then working capital, which is the one most often underwritten last and the one that has killed the most plants. The Packers and Stockyards Act requires payment for livestock by the close of the next business day (7 U.S.C. §228b). A 1,500-head-a-day plant buys about $5 million of cattle every day at 2026 prices and collects from customers weeks later; fifteen to twenty-five days of float is $75 million to $125 million of revolver that the SPUR term loan does not provide. Northern Beef Packers in Aberdeen, South Dakota, opened in 2012 with $138.8 million of liabilities against $79.3 million of assets, "lacked money to buy cattle," and was sold out of Chapter 11 for $44.3 million, of which $4.8 million was cash and the rest a credit bid. Pure Prairie's bank would not raise its line from $7.5 million to $12 million, and the plant stopped (19). Liquidation value of a single-purpose slaughter plant has run between 10 and 35 percent of cost in the cases we can document. Collateral does not save these credits. Cash flow and sponsors do.
Labor and freight close the list. Regional beef runs about 0.53 to 0.60 full-time employees per head of daily capacity, mid-scale plants closer to 0.75 to 0.80, and very small plants three to four times that; the median slaughterer in food manufacturing earned $19.85 an hour in May 2025 (35). The workforce is immigration-dependent and contested at the county level. Reefer spot rates were $2.76 a mile excluding fuel in October 2026, up 32.7 percent on the year, which is a structural penalty on plants sited for cattle access and far from the people who eat beef.
The pattern across the failures we know, Northern Beef Packers, Pure Prairie, HyLife's Windom plant that closed in June 2023 citing grain costs, exchange rates and operating losses, is the same three causes: supply that was mapped rather than contracted, liquidity that ran out during ramp, and a spread that moved against a plant with no cushion. The successes, Sustainable Beef, True West Beef, America's Heartland, paired producer equity or a strategic offtaker with patient capital and an experienced operator. Sponsor quality predicts outcomes better than plant design does.
How the lender will underwrite it
Because SPUR defaults to OneRD, the credit file is a B&I file with a larger number on the front. The rules that govern it are specific, and it helps to separate what is a rule from what is a convention.
The rule on credit is §5001.202. The lender must produce a written evaluation of the five Cs "consistent with generally accepted prudent lending practices for commercial, public and project financing," a global cash-flow and coverage analysis across affiliates and guarantors, a review of every contract, management agreement and lease, and, in its own words, a written evaluation of the feasibility study and engineering reports (5). For a processing plant the paragraph that matters is §5001.202(b)(5), which lists feedstock availability and depth, offtake agreements, technical feasibility, construction complexity and the strength of the contractor among the conditions the lender must address. Those are the same items the NOFO puts in the feasibility study. The two documents are meant to agree.
The rule on collateral is §5001.203, and it contains the sentence that decides most of these credits: "If an appraisal is received containing any value attributed to business valuation or as a going concern, the business valuation or going concern value must be deducted from the reconciled market value prior to discounting" (5). A single-purpose slaughter plant is therefore collateralized on real property and equipment only, with discounts that must reflect "type, quality, location, marketability, and alternative uses" and be justified in writing. There is no regulatory advance rate and no fixed minimum coverage ratio for new money in Part 5001; the only numeric floor, 1.1x historical coverage, applies when refinancing is the majority purpose (5). The levels you will actually see, 50 to 70 percent on special-purpose real estate, 50 to 70 percent on equipment, 1.20x to 1.30x coverage at stabilization, are bank policy, not USDA rule, and should be labeled as such in the memo. Expect a collateral shortfall on any plant that costs more to build than it would sell for, which is most of them, and expect §5001.204 to fill it: unsecured guaranties from every owner of 20 percent or more, for the full term, sized to the guarantor's share of the loan (5).
The rule on equity is §5001.105(d), and it bites hardest exactly where SPUR borrowers will want it least. A greenfield plant that wants the guarantee in place during construction is a "new business, construction, loan note guarantee before completion" and needs at least 25 percent tangible balance-sheet equity or a 25 percent injection, in cash or earning assets, injected before any guaranteed funds are disbursed (5). Appraisal surplus does not count. Subordinated debt counts only if it is cash on standstill for the life of the loan.
The rule on construction is §5001.205(e)(2), and it is where loss claims are lost. To issue the guarantee before completion the lender must evidence a fixed-price contract with an independent general contractor, an independent disbursement and monitoring firm or demonstrated in-house capacity, a budget and timetable confirmed by an independent engineer including contingency and start-up working capital, contractor vetting or a 100 percent performance and payment bond, and, where integrated processing systems are involved, an independent technology firm's completion guarantee (5). Monthly reporting follows: engineer certification of each draw, lien waivers, equity and funds disbursed to date. The guarantee is unenforceable to the extent of loss from "use of Loan proceeds for unauthorized purposes, negligent Loan origination, negligent Loan servicing, or failure to obtain or maintain" required security, and the Agency "may reduce any loss payment" for noncompliance (5). Full denials are rare; the OCC counted claims on 19, 15 and 38 loans in FY2021 through FY2023 with one partial denial (36). The Inspector General's Georgia audits show how the partial ones happen: a lender that applied $75,000 of guaranteed funds to its own unguaranteed loan and misrepresented construction progress faced a recommended $3.7 million reduction.
The economics are then straightforward. On a $100 million SPUR loan the lender pays, or passes through, $2.7 million up front and about $495,000 a year in retention fees, holds $10 million of unguaranteed exposure that cannot be participated, and can sell $90 million of guaranteed portion once the note is fully disbursed (2, 5). Broker-quoted premiums of 6 to 11 percent on guaranteed paper are marketing figures, not transaction data, and shrink on fixed-rate or long-term notes without prepayment protection. The guaranteed portion is typically 20 percent risk-weighted and may sit outside the legal lending limit (36). The 10 percent retention is the binding constraint on a balance sheet, and it is 33 percent more than B&I's 7.5 percent.
One structural point on the deferral. Interest accrues through it. The first annual interest payment is due no later than month 24 and level amortization no later than month 36 (1). The prudent structure is a funded interest reserve, which is an eligible project cost, sized to construction plus a documented ramp, with a debt-service reserve that covers the end of the deferral. The deferral does not remove the stress test. It moves it to the first amortizing year, which is also the year the plant is supposed to reach design.
Who will lend is an open question. USDA's own data are the authority, and the lender list changed in May 2026 when the Agency removed ten lenders holding nearly half of its delinquencies, several of them among the largest-volume originators of the prior cycle (21). X-Caliber Rural Capital, USDA's top OneRD lender by volume for FY2023, and First National Bank of Oklahoma were first to market with SPUR programs within a week of the NOFO. Non-regulated lenders can be approved under §5001.130(c) for up to five years on audited financials, a 6 percent delinquency ceiling and a 1 percent loss reserve (5).
A comparison closes the section, because clients ask. Against B&I, SPUR offers seven times the loan size, a higher guarantee, urban eligibility and a longer interest holiday at the cost of higher retention and a mandatory study. Against SBA 7(a) and 504, it is simply a different order of magnitude, with a $5 million and $5.5 million ceiling respectively on the SBA side and a lighter feasibility regime; a slaughter plant is a classic special-purpose property under SOP 50 10 8, which drives SBA's injection to 15 or 20 percent but does not mandate a study. Against Farm Credit, which has no cap and no guarantee, the question is eligibility: producer ownership above 50 percent or producer supply of at least 20 percent of throughput under 12 CFR 613.3010. For a producer-owned plant the honest answer is often a Farm Credit senior facility beside a SPUR-guaranteed term loan, not one instead of the other.
The hardest page in the file
Under the Business and Industry rule, an independent feasibility study is mandatory only "for guaranteed loans greater than $1,000,000.00 to a new business," and the Agency may reduce its scope where the lender's analysis is sufficient (5). The OneRD FAQ goes further and says a lender's discussion of project risks "may negate the need for an independent feasibility study" (38). SPUR removes all of that. NOFO §5.2(b)(vii) begins: "A feasibility study of the proposed project, by a qualified consultant, is required" (1). No threshold, no new-business trigger, no discretion to waive. It applies to the refinancing of an operating plant as much as to a greenfield.
The section then specifies the study in more detail than any B&I guidance we have read. At a minimum it "must include an evaluation of the economic, market, technical, financial, and management feasibility and an executive summary that reaches an overall conclusion as to the business' chance of success." It "must consider the borrower's management experience; sources of capital; products, services, and pricing; marketing plan; proposed use of loan funds; availability and access to labor, raw materials including animals and product, and supplies; availability or access to necessary infrastructure including water and waste disposal; worker and food safety plans; contracts in place; and distribution channels." It "should address and quantify how the project will increase capacity or make the Processing of Meat, Poultry, or Seafood more resilient, diverse, or secure." And it must "corroborate that the borrower meets the borrower eligibility provisions" and carry the market-share self-certification against the fourth-largest firm (1). We count twenty-one elements, seven with "must include," twelve with "must consider," one with "should… quantify," and one certification. Reviewers will check the "must" items first.
Independence comes from the regulation, not the NOFO. The NOFO adopts the definitions in §5001.3, under which a qualified consultant is "an independent third-party person possessing the knowledge, expertise, and experience to perform the specific task required" and a feasibility study is "a report including an opinion or finding conducted by an independent qualified consultant(s)… as outlined in appendix A" (5). The lender must report every conflict of interest to the Agency in writing under §5001.208 (5). USDA's audit record shows what that language is for. A 2002 Inspector General audit of B&I lending in Hawaii found that a state office "accepted business plans prepared by the borrowers as meeting regulatory requirements" and "allowed a consultant to submit a feasibility study even though the office noted the consultant was part owner of the company requesting funding"; seven of the eleven loans went delinquent or into bankruptcy (23). A business plan with a new cover is not a study. Neither is the income approach of an appraisal, a sentence the legacy B&I rule said outright and the NOFO merely stopped repeating.
Three features of the requirement are easy to miss. First, the NOFO puts the eligibility corroboration and the market-share certification inside the third-party study. A consultant should corroborate the share using named, dated industry or NASS data and leave the certification itself to the borrower; the two are different acts. Second, the study must reconcile with the borrower's executive summary, which §5.2(b)(iv) requires to describe the same capacity and resilience contribution and to address "the criteria for priority scoring as described in Section 7.1," a section that contains no criteria and only cites §5001.315 (1). Expect the B&I schedule in §5001.318 to apply by analogy until USDA says otherwise, and have the study substantiate every point the application claims. Third, USDA's free technical assistance through the AMS Meat and Poultry Processing Capacity Technical Assistance program may help with a business plan but, in the NOFO's words, "will not include co-drafting guaranteed loan application elements" (1, 39). The study is a paid, independent deliverable by design.
Sequencing is the other thing the study has to get right, because it feeds the environmental record. Under 7 CFR 1b.2(h)(3), "the environmental review process must be concluded before the obligation of funds" for Rural Development programs, and obligation accompanies the conditional commitment (37). A borrower who buys property, orders equipment or starts construction after the complete application but before the conditional commitment "assumes all risks" under §5001.315(f), and incurring obligations that limit alternatives "could result in project ineligibility" under §5001.207 (5). The study's technical section, site, water source, wastewater, rendering and offal, truck traffic, and the NEPA analysis must describe the same project. Change the site after the review and both reopen; under §5001.303(d) a modified application is a new one (5). Build the study on a frozen project definition, and start the environmental submission early, which the NOFO expressly allows (1).
What a reviewer actually tests in a protein-plant study is a short list, and it is the same list this piece has been building. Animal supply: herd inventory within the procurement radius, producer commitments or member delivery obligations, seasonality, and the competing buyers who are bidding for the same cattle. A plant at 60 head a week needs at least 3,120 head a year, and most producers in a county sell fewer than 50. Utilization: a ramp that matches the deferral and the three-year amortization start, with sensitivity at 60 to 80 percent of design. Water and waste: a will-serve letter, gallons per head (300 to 450 for beef on the NMPAN benchmark), pretreatment terms, a rendering or disposal contract priced as a cost. Labor: local wage data against the $19.85 median and a named training partner. Management: an operator with prior profit-and-loss responsibility for a plant of similar size and a documented path to the grant of inspection. Contracts: offtake, supply and toll agreements with terms that match the loan, not letters of intent. And a quantified capacity claim, head or pounds per year, with the regional share before and after.
The NOFO sets no date-currency rule for the study and no SPUR-specific appendix. It simply requires the opinion. The study that will carry a SPUR application through a State Office and a loan committee is the one that reaches a conclusion on the chance of success, says why, and shows its work on the four variables that have historically decided the outcome.
What this means if you are building the file
First, make funding a condition precedent, in writing. Before anyone pays for an appraisal, an engineer or a study, ask the Rural Development State Office and OneRDGuarantee@usda.gov to confirm the budget authority behind the $5 billion and whether the conditional commitment will be issued subject to availability of funds. The program page and the NOFO disagree, and the appropriation the NOFO cites has been rescinded twice on the face of the statutes (1, 3, 7, 8). This is a one-paragraph email that protects six figures of third-party cost.
Second, size the borrower group before sizing the loan. The $175 million cap counts every affiliate whose revenue the plant depends on, both portions of the loan, and any SPUR balance already outstanding (1). Expect the Agency to require co-borrowers under §4.1(k). A holding-company structure should get a written Agency reading of "Independently Owned and Operated" before the term sheet, because the NOFO's definition, read literally, excludes subsidiaries, and its own co-borrower provisions assume them.
Third, underwrite to the base rule, not the marketing. Model §5001.105(d) equity at 25 percent for any greenfield that wants the guarantee during construction, deduct going-concern value from every appraisal before discounting, and assume liquidation recovery on the plant of 10 to 35 percent of cost. Then fill the gap the way the rule expects: guaranties from every 20 percent owner, assignment of offtake contracts, and a debt-service reserve that carries the plant to the end of the deferral (5).
Fourth, fund the animals separately. Put a working-capital revolver sized to 15 to 25 days of livestock purchases beside the term loan, with a minimum liquidity covenant equal to two quarters of negative margin. The SPUR loan builds the plant. It does not buy the cattle, and the prompt-payment rule means the plant will need to.
Fifth, contract the supply before the study is written, because the study has to report it. Producer equity tied to delivery obligations, as at Amarillo with its 700,000-head commitment, formula grids and co-op structures are the forms that have worked. A covenant requiring 60 to 80 percent of year-two throughput under signed agreements is a reasonable ask, and a plan to underwrite Mexican feeder volume beyond the two ports ERS assumes is not.
Sixth, build the construction package on day one. A fixed-price contract with an independent general contractor, a 100 percent performance and payment bond, an independent disbursing agent and an engineer-certified budget with 10 to 15 percent contingency and 4.5 percent annual escalation are the §5001.205(e)(2) items, and they are also the items whose absence reduces a loss claim later (5).
Seventh, freeze the project definition and start the environmental review early. The study, the engineering and the NEPA record must describe the same plant on the same site, and the borrower must not buy, order or build between the complete application and the conditional commitment without written Agency authorization under 7 CFR 1b.2(h)(2) (37).
Eighth, commission the study as a study. Twenty-one elements indexed to page numbers; an independent author with a signed no-conflict statement filed under §5001.208; an executive summary that states a conclusion on the chance of success; a sensitivity case at 60 percent utilization with drop credits at cyclical lows; and a market-share corroboration on named, dated data for the species being financed. What we do differently in an engagement of this kind is treat the animal-supply analysis and the wastewater capacity as the opening chapters, not the appendices, and write the management section as if the reviewer has read the 2002 Hawaii audit. They have.
Minimum equity gets a plant approved. Contracted supply gets it to breakeven. The study is where a reviewer finds out which one you have.
Current as of November 2, 2026
This piece reflects the FY2027 SPUR NOFO published October 23, 2026, the Federal Register notice at 91 FR 67540 published October 27, 2026, the Rural Development program page as modified October 26, 2026, and 7 CFR Part 5001 as current on eCFR (1, 2, 3, 5). Four items are unresolved in the primary text and should be rechecked before reliance: the funding source and the "pending Congressionally approved funds" language; the application-open date, October 23 in the NOFO and October 27 in the Federal Register; the fee effective date, which the Federal Register gives as October 1, 2027 for a notice titled FY2027; and the priority-scoring criteria, which §5.2(b)(iv) references and §7.1 does not contain. No FY2027 B&I fee notice and no correction to FR Doc. 2026-21858 had been published as of this date. We will update this page when USDA issues a correction, a scoring schedule, or a written position on funding, and on each annual fee notice thereafter.
Questions lenders and borrowers actually ask
Is this the same SPUR program that paid beef plants this summer?
No. The June 30, 2026 program is a $500 million FSA payment program under the CCC Charter Act for beef slaughter plants, and its window closed September 30, 2026 (9, 10). The loan program is a Rural Development guarantee under ARPA §1001(b)(4) covering meat, poultry and seafood (1). Nothing in either text links them.
Can a start-up apply?
Yes. The NOFO covers borrowers "engaged in or proposing to engage in" processing, and custom-exempt plants may apply as new or expanded businesses seeking inspection (1). A start-up must hold a valid certificate of inspection by the time the loan note guarantee issues, and a greenfield wanting the guarantee during construction faces the 25 percent equity bracket under §5001.105(d) (1, 5).
Is the $175 million per loan?
No. It is the aggregate for the borrower and dependent affiliates, counting the guaranteed and unguaranteed portions and any existing SPUR balance (1). USDA's own program page and fact sheet say "maximum loan amount," which is shorthand; the NOFO controls.
Does the two-year deferral mean no interest?
No. Interest accrues. The first annual interest payment is due no later than two years from the note, and the first full principal and interest payment no later than three years (1). An interest reserve is an eligible project cost and the prudent way to fund it.
Is equity required?
The NOFO is silent, which means the B&I table in §5001.105(d) applies by default: 10 percent for an existing business, 20 percent for most new businesses, 25 percent for a new business seeking a pre-completion guarantee, measured in cash or earning assets at closing (5). We would obtain written Agency confirmation, and we would not rely on any marketing that says otherwise.
Who fails the market-share test?
On current data, the top four in each named species: in beef, JBS, Tyson, Cargill and National Beef; in chicken, Tyson, Pilgrim's, Wayne-Sanderson and Mountaire; in turkey, Butterball, Jennie-O, Cargill and Farbest; in pork, Smithfield, JBS, Tyson and the fourth packer by whichever metric USDA accepts (42). Seafood is exempt (1). The NOFO does not name the metric, so a borderline firm's eligibility may turn on the dataset.
Is a feasibility study really required if we are refinancing an operating plant?
On the NOFO's text, yes. Section 5.2(b)(vii) requires a study in every full application with no threshold and no waiver language (1). The OneRD FAQ's statement that a lender's analysis may negate the need for a study describes the base program, not SPUR (38). Confirm scope with the State Office, but plan for the full twenty-one elements.
Can USDA's free technical assistance write the study?
No. The NOFO says MPPTA services "will not include co-drafting guaranteed loan application elements," and the study must be by an independent qualified consultant under §5001.3 (1, 5, 39). A study authored by a technical-assistance provider, a packager, or anyone with equity or contingent compensation is the fact pattern the 2002 Inspector General audit documented (23).
How long does USDA take?
Not published for SPUR. The B&I goal is 30 to 60 days after a complete application, per the OCC (36). The NOFO says awards come "not earlier than 30 days after announcement," and the window runs until funds are exhausted (1). The environmental review must conclude before obligation, and for a greenfield that is usually the longer clock (37).
What should we expect a SPUR-grade study to cost and take?
There is no independent survey. Published vendor ranges for USDA studies run from under $10,000 to $50,000 and four to twelve weeks. A study on a $25 million to $175 million plant with a livestock-shed analysis, wastewater engineering inputs and FSIS timing will sit at or above the top of that range, and the data room, not the writing, sets the schedule.
November 2, 2026, by Michal Mohelsky, principal of MMCG Invest, LLC, a national SBA and USDA feasibility study consultancy. Book a 30-minute scoping call.
This article is analysis and commentary for lenders, borrowers and investors. It is not legal, accounting or investment advice, and it does not create a consulting relationship. Program terms are quoted from the primary text as of the date above and may change; readers should verify current requirements with USDA Rural Development and their own counsel before acting.
Cite this
Mohelsky, M. (2026). SPUR Is Not a Small-Processor Program. The Feasibility Study Is Where It Will Be Decided. MMCG Invest, LLC, Insights. Published November 2, 2026.
Sources
- USDA Rural Development, Strengthening Processing for US Ranchers (SPUR) Guaranteed Loan Program, Fiscal Year 2027 Notice of Funding Opportunity, publication date October 23, 2026 (primary).
- Federal Register, FR Doc. 2026-21858, 91 FR 67540, October 27, 2026 (primary).
- USDA Rural Development, SPUR program page, FAQ for Lenders and Borrowers, and fact sheet, page modified October 26, 2026 (primary).
- USDA, press release, "Trump Administration Announces $5 Billion SPUR Guaranteed Loan Program," October 23, 2026 (primary).
- 7 CFR Part 5001, OneRD Guaranteed Loan Program, as current on eCFR; §§5001.3, 5001.105, 5001.130, 5001.202 to 5001.208, 5001.303, 5001.306, 5001.315, 5001.318, 5001.402, 5001.408, 5001.454 and 5001.455 (primary).
- American Rescue Plan Act of 2021, Pub. L. 117-2, §1001 (primary).
- Fiscal Responsibility Act of 2023, Pub. L. 118-5, Division B, Title I, Section 9, 137 Stat. 26; rescission acknowledged in USDA apportionment footnotes on openomb.org (primary).
- Keep Kids Fed Act of 2022, Pub. L. 117-158, §4(a)(1)(A) (primary).
- USDA, press release, Secretary Rollins announces SPUR program support for small and mid-size beef processors, June 30, 2026 (primary).
- USDA Farm Service Agency, Strengthening Processing for U.S. Ranchers (SPUR) Program page (primary).
- Executive Order 14424, Promoting Fair Competition in Livestock Markets and Expanding Market Access for American Meat Producers, September 4, 2026, 91 FR 57761; USDA release of the same date (primary).
- Executive Order 14276, Restoring American Seafood Competitiveness, April 17, 2025, 90 FR 16993 (primary).
- Federal Register, Notice of Funding Opportunity for the Food Supply Chain Guaranteed Loan Program, FR Doc. 2021-26693, December 9, 2021 (primary).
- USDA, Food Supply Chain Guaranteed Loan awards list, as of November 14, 2023 (primary).
- USDA, press release, final awards through the Meat and Poultry Processing Expansion Program, September 19, 2024 (primary).
- USDA Office of Inspector General, Inspection 34801-0001-21, MPPEP Oversight of Grant Recipients' Use of Funds, December 23, 2024 (primary).
- USDA Office of Inspector General, Audit 34601-0001-21, Controls Over the MPPEP Award Process, Phase 1, March 5, 2024 (primary).
- Letter to USDA regarding Pure Prairie Poultry from Reps. Finstad, Feenstra, Van Orden, Thompson and Sens. Grassley, Ernst, Boozman et al., October 25, 2024 (primary).
- DTN/Progressive Farmer, "USDA Looking into Claims Poultry Growers Weren't Paid in Failed Broiler Plant," October 9, 2024 (secondary).
- Charles City Press, on the Community Bank & Trust credit bid approved May 30, 2025, and the Pitman Farms purchase (secondary).
- USDA Rural Development, stakeholder announcement, revocation of approved-lender status for ten lenders, May 13, 2026 (primary).
- Summit LLC for the National Rural Lenders Association, USDA B&I Guaranteed Loan Program Economic Assessment 2025, submitted to the House Agriculture Committee, September 18, 2025 (secondary, built on a FOIA dataset).
- USDA Office of Inspector General, Audit 34601-6-SF, Rural Business-Cooperative Service B&I Direct Loans, Hawaii, September 2002 (primary).
- USDA NASS, Cattle, January 30, 2026 (primary).
- USDA ERS, Livestock, Dairy, and Poultry Outlook, LDP-M-388, October 16, 2026 (primary).
- Meatingplace, "Cutout dip guts beef packer margins," October 29, 2026, reporting Sterling Marketing (secondary).
- High Plains Journal, "Beef packers adjusting to low cattle inventory," August 28, 2026 (secondary).
- USDA AMS, Packers and Stockyards Division, Combined 2023 and 2024 Annual Report (primary; CR4 figure as reported).
- NOAA Fisheries, Fisheries of the United States, import share of consumption, 2024 (primary).
- USDA FSIS, Revising Establishment Size Definitions, docket FSIS-2026-0001, establishment counts as of December 2025 (primary).
- Meat+Poultry, "USDA awards $57 million to expand meat processing capacity," October 2026, reporting MPPEP Phase 4 tentative awards (secondary).
- KNOP News 2, "North Platte's Sustainable Beef reaches major milestone," February 7, 2026 (secondary).
- Meat+Poultry, "America's Heartland Packing holds open house," September 2025 (secondary).
- USDA AMS, National Weekly Steer and Cow Drop Credit reports (NW_LS441, NW_LS444), September 2025 through October 23, 2026 (primary).
- U.S. Bureau of Labor Statistics, Occupational Employment and Wage Statistics, May 2025, SOC 51-3023 Slaughterers and Meat Packers (primary).
- Office of the Comptroller of the Currency, Community Developments Insights, USDA Business and Industry Guaranteed Loan Program, June 2025 (primary).
- 7 CFR Part 1b, USDA National Environmental Policy Act procedures, as amended at 91 FR 17062 (April 3, 2026) and 91 FR 40353 (July 2, 2026) (primary).
- USDA Rural Development, OneRD Guarantee Loan Initiative page and FAQ, modified October 22, 2026 (primary).
- USDA AMS, Meat and Poultry Processing Capacity Technical Assistance Program; Flower Hill Institute, MPPTA program description (primary).
- Rider Levett Bucknall, Quarterly Construction Cost Report, Q3 2026 (secondary).
- USDA, press release, Rural Development loan guarantee for a new beef processing facility in Dimmitt, Texas, October 29, 2026 (primary).
- WATT PoultryUSA, 2025 rankings of U.S. broiler and turkey companies by weekly ready-to-cook and live weight (secondary).
- USDA, press release, "Secretary Rollins Announces Ranchers First Initiatives," August 31, 2026 (primary).
- USDA NASS, Livestock Slaughter 2025 Summary, April 22, 2026 (primary).
- Drovers, "Too many plants, not enough cattle: inside the beef packing capacity squeeze," 2026, reporting Sterling Marketing's John Nalivka (secondary).
- Terrain / Farm Credit Services of America, Beef Quarterly Outlook, Q3 2026 and Q1 2026 (secondary).
Cite this
Michal Mohelsky, J.D., FMVA (2026). SPUR Is Not a Small-Processor Program. The Feasibility Study Is Where It Will Be Decided. MMCG Invest, LLC. https://www.mmcginvest.com/post/usda-spur-guaranteed-loan-program-feasibility-study
Where this goes next
- USDA Feasibility StudyMMCG's feasibility study page for this subject.