A 13,140-square-foot flex building built in 2005 at 10051 W Emerald Street in Boise, listed at $2,700,000, converted by a hypothetical established managed services provider into a 600 kW edge data center that houses the provider's own 200 kW of racks and sells up to 400 kW of retail colocation. Underwritten under SBA 504 with a 7(a) companion at a total project cost of $11,081,312, restructured to a 15 percent injection of $1,408,688, a $3,377,000 debenture, a $4,695,625 first lien and a $1,600,000 7(a). The facility never covers its own debt, with project DSCR peaking at 0.39x, and is financeable only on the borrower's global cash flow, which covers 1.02x in Year 1 and 1.73x in Year 5 after owner distributions. The 504 job test fails at about 5 jobs against 36 required, so eligibility runs through the 13 CFR 120.862(b)(11) energy-reduction route on a modeled 15.6 percent reduction. Determination: not approvable as proposed; feasible as restructured on global credit, with an engineer-certified energy baseline and customer-concentration evidence as conditions.
Model study prepared by MMCG Invest | Michal Mohelsky, J.D., FMVA | 4 October 2026
Study at a Glance
| Item | Finding |
|---|---|
| Subject | 10051 W Emerald Street, Boise, ID 83704 (Building 9); 13,140 square feet, flex, built 2005 |
| Listing | LoopNet, TOK Commercial, asking $2,700,000; listing ID, days on market, acreage, zoning and power service not captured (see Conditions) |
| Program | SBA 504 (CDC debenture plus third-party first lien) with a 7(a) companion for short-lived assets; SOP 50 10 8.1 governs loans numbered on or after 1 October 2026 |
| Borrower (hypothetical) | Established Treasure Valley MSP, 12 years operating, $12.0 million revenue, 55 staff, NAICS 518210; migrating 40 cabinets and 200 kW from a leased third-party facility |
| Operating program | 600 kW critical IT; 200 kW borrower load plus up to 400 kW third-party retail colocation; 120 kWdc rooftop solar |
| Total Subject Project Cost | $11,081,312 ($18,469 per kW) |
| Capital stack (restructured) | First lien $4,695,625 at 7.25 percent; 504 debenture $3,377,000 at 6.54 percent effective; 7(a) $1,600,000 at 9.75 percent variable; borrower injection $1,408,688 (15 percent of the 504 project) |
| Annual debt service | $998,201 new debt; $1,248,201 global including $250,000 of existing operating company debt |
| Project DSCR | (0.24x), 0.01x, 0.22x, 0.33x, 0.39x in Years 1 to 5 |
| Global DSCR after distributions | 1.02x, 1.27x, 1.49x, 1.63x, 1.73x |
| Occupancy test (51 percent, existing building) | 63.7 to 81.4 percent borrower occupancy depending on shared-space classification; passes |
| Job test | About 5 jobs against 36 at $95,000 or 23 at $150,000; fails on jobs alone |
| Energy route | 15.6 percent modeled reduction against a 1.54 PUE baseline; passes 13 CFR 120.862(b)(11), subject to engineer certification |
| Determination | Not approvable as proposed; feasible as restructured on global credit with conditions |
Determination
MMCG concludes that the project is not approvable as proposed. The proposal carries a 10 percent injection, a $3,859,000 debenture and job-based 504 eligibility. The job opportunity test fails: the facility supports about 5 positions against the 36 a $3.4 million debenture requires at $95,000 per job, or 23 at $150,000. The special purpose question is unresolved, and a 10 percent injection does not survive a special purpose classification.
As restructured, the project is feasible on global credit and only on global credit. The restructuring carries a 15 percent injection of $1,408,688, a $3,377,000 debenture under the 13 CFR 120.862(b)(11) energy-reduction route, an Eligible Passive Company holding structure, the existing building under the 51 percent occupancy test, the short-lived IT and controls moved to a $1,600,000 7(a), and a $417,500 ramp reserve. On that basis global DSCR after owner distributions runs 1.02x in Year 1, below the 1.15x floor and covered by the reserve, then 1.27x, 1.49x, 1.63x and 1.73x. The facility on its own never covers its debt: project DSCR peaks at 0.39x in Year 5, because a 24-hour staffing floor spread over 600 kW consumes 30 percent of revenue and the borrower's own load is carried at a transfer price 23 percent below the incumbent's rate. The lender is underwriting an MSP that is buying its own building, not a data center.
Eligibility rests on three judgement calls that the lender and CDC must confirm: that assigned-cabinet colocation at 9 percent of combined revenue is service revenue rather than space rental under SOP 50 10 8, Section A, Chapter 1, Paragraph E.3; that the improved building is not special purpose property, with the restructured case underwritten at the 15 percent tier regardless; and that the 15.6 percent energy reduction, measured against an industry-average baseline rather than the incumbent's metered PUE, satisfies 120.862(b)(11). The determination is conditioned on an engineer-stamped baseline using the incumbent facility's metered consumption and a contractual design PUE of 1.35 or better, customer-concentration evidence showing the top three customers under 15 percent of revenue, a written CDC determination on special purpose status, a covenant capping third-party space at data hall B, and vacant delivery of the building.
Scope and Basis of This Model Study
This is an MMCG model study: a feasibility analysis performed on a real, publicly listed building using public data only, prepared to show CDCs, SBA lenders and operators how MMCG underwrites a small owner-operated data center under SOP 50 10 8 and 8.1 when the facility cannot carry its own debt and eligibility runs through the energy public policy route rather than job creation. The borrower is a hypothetical, unnamed regional MSP; its revenue, headcount, racks, customer base and financial statements are MMCG assumptions set without a sourced industry benchmark, which is disclosed. MMCG has no relationship with the seller or listing broker, and the analysis is not an offer, an appraisal or a recommendation to buy the building. Real companies appear only as competitors or cited comparables. Every figure carries a documentary source or is labeled MMCG assumption. Items not verified from a primary source are listed in Conditions and Limitations. All SOP 50 10 8.1 content, including DSCR floors, is carried as reported by lender trade summaries of Information Notices 5000-880695 and 5000-882227 and must be confirmed against the SOP text in the lender's file.
Project Business Plan
The borrower, an established MSP operating for 12 years, moves its hosted platform of 40 cabinets and 200 kW contracted (140 kW drawn) from a leased third-party facility into a building it owns, and sells the balance of a 600 kW critical load as retail colocation to Treasure Valley businesses. The physical program converts the 2005 flex building into two data halls, a 1,500-square-foot hall for the borrower and a 2,700-square-foot hall for third-party cabinets, with new electrical, UPS and battery rooms, a NOC, 3,000 square feet of MSP office, a telecom entrance room, an exterior generator yard and cooling plant pad. The electrical design is a new 2,000-amp, 480-volt service on a utility pad-mount transformer, N+1 switchgear, UPS with lithium-ion batteries, and two 1,000 kW generators with 24-hour fuel. Cooling is a closed-loop plant with containment at a design PUE of 1.35. A 120 kWdc rooftop array supplies part of the facility's own consumption. The borrower occupies its hall, office and NOC; third-party customers occupy assigned cabinets in hall B. The real estate sits in an Eligible Passive Company that leases 100 percent of the building to the operating company for at least the loan term at rent capped at debt service plus holding costs, with the operating company as co-borrower and every 20 percent owner as guarantor.
Marketing and Sales Strategy
The anchor is the borrower's own migrating load, which fills a third of the facility on day one and is why occupancy clears in every year. Third-party sales target the regulated institutions in the valley that carry disaster recovery and compliance drivers: regional banks and credit unions, hospital systems, insurers, Ada County and city government, and school districts. The sales case against the incumbent is price, at 23 percent below the published $300 per kW per month, and the operator's existing relationships as the valley's MSP. A half-time sales position sits in facility payroll; commissions are carried at 3 percent of third-party revenue.
Amenities
- 120 cabinets across two halls; 5 kW standard
- N+1 UPS and cooling; two 1,000 kW generators, N+1
- Two diverse fiber entrances; IP transit resold at the incumbent's published tiers
- 24-hour NOC staffed by the MSP
- Customer staging, secure access, DCIM portal
Site and Location Analysis
The subject is Building 9 at 10051 W Emerald Street in west Boise, a 13,140-square-foot flex building built in 2005, listed on LoopNet by TOK Commercial at $2,700,000; CityFeet names the broker as Tyler Martin. The building's slab capacity, clear height, column spacing, roof age, existing amperage and voltage, and HVAC are not published and the assessor record was not reached; the budget carries a new 2,000-amp service, $60,000 of slab reinforcement under the UPS and battery rooms, and $180,000 of structural and roof modification as MMCG assumptions. Yelp lists a tenant in Suite 120, so vacant delivery must be confirmed, because the occupancy test must be met within one year of closing.
The corridor is the strongest evidence for the use. ValorC3 Boise 1 at 10215 W Emerald Street, on the same street, advertises a 46 MW dedicated substation with 22 MW of redundant service, and the City of Boise approved ValorC3's 38,000-square-foot, 10 MW data center at 9601 W Emerald Street (BoiseDev, 26 March 2026), with an expansion application filed before opening. The trade area is the Treasure Valley, Ada and Canyon Counties, defined by latency; the incumbent markets sub-5-millisecond latency to the valley from its Boise facility.
A new-build alternative was priced and rejected: a 1.09-acre commercial lot at 1471 S Eagle Flight Way, listed at $1,000,000 by TOK Commercial beside Ark Data Centers Boise 2. Under the conservative space classification the new build fails the 60 percent test with its 20 plus 20 leasing allowance once third-party load passes about 100 kW, which is why the existing building governs.
Zoning and Entitlement
The subject's district is inferred as I-1, Industrial: Light, because a neighboring Emerald Street parcel is marketed as M-1D and Boise's code rewrite maps M-1 into I-1; the district is unverified. Boise describes I-1 as accommodating technology-related land uses with a 55-foot height maximum. Table 11-03.1 has no data center row in the portions reviewed, and Section 11-03-01 sends unlisted uses to a Planning Director interpretation, which the study treats as a condition. I-1 bars uses that store hazardous substances regulated under 40 CFR, which bears on diesel storage and battery chemistry and is carried as a condition. Generator-testing noise limits, screening standards and solar permitting under Title 11 were not researched. ValorC3's approval at 9601 W Emerald is the strongest local evidence that the use is approvable on this corridor.
Utilities, Fees and Property Tax
Electric. Peak facility load is about 810 kW (600 kW IT at a 1.35 PUE), below the 1,000 kW threshold of Idaho Power Schedule 19, so initial service is Schedule 9 Large General Service, secondary, effective 1 January 2026: a $25 monthly service charge, a $1.84 per kW basic charge, demand of $9.49 per kW in summer and $7.75 in non-summer, and energy of 5.0908 cents per kWh in summer and 4.9875 cents in non-summer. Schedule 19 becomes mandatory at 1,000 kW or more in three of twelve billing periods, with billing demand floored at 1,000 kW, a $110 service charge, a $2.27 basic charge, demand of $14.46 summer and $13.05 non-summer plus an on-peak charge of $2.51 in summer, and energy of 4.1894 to 5.9565 cents. Schedule 19 is available where existing facilities of adequate capacity exist; substation or transmission additions need a separate agreement. Line extensions fall under Rule H, whose three-phase allowance for Schedule 9 is $8,921. Idaho Power's Schedule 20, Speculative High-Density Load, was not reviewed and is carried as a condition. The modeled effective cost is about 7.2 cents per kWh including an assumed 10 percent rider adder, against the EIA US commercial average of 13.51 cents (April 2026).
Solar. A 120 kWdc fixed rooftop array at 10 degrees tilt on about 60 percent of the roof, output 165,600 kWh a year on an engineering estimate of 1,380 kWh per kWdc (PVWatts was not run; MMCG assumption), installed at $2.25 per watt, $270,000 (MMCG assumption). Idaho Power Schedule 84 provides real-time net billing for large general service customers with an annually updated export credit rate under IPUC Order No. 36785 (30 September 2025); the facility's load always exceeds the array's output, so exports are about zero and the solar value is avoided energy at the Schedule 9 rate. Treatment of any federal credit is a question for the borrower's tax counsel; the model assumes none.
Energy baseline for 13 CFR 120.862(b)(11). The method compares the borrower's own load, 140 kW average IT, at its current leased facility with the same load at the subject.
| Case | PUE | Solar credit | Annual kWh |
|---|---|---|---|
| Baseline, current facility | 1.54 (Uptime Institute 2025 industry weighted average, used as a proxy because the incumbent publishes no PUE; the survey's 1.48 for facilities built in the last five years would shrink the reduction) | None | 1,888,656 |
| Subject, design PUE only | 1.35 (MMCG design assumption) | None | 1,655,640 (12.3 percent lower) |
| Subject, design PUE plus solar | 1.35 | 37 percent of output allocated by load share, 61,330 kWh | 1,594,310 (15.6 percent lower) |
The modeled reduction of 15.6 percent clears the 10 percent test. It is not settled that a leased third-party facility counts as the existing facility, or that the test is measured per unit of IT load, because total site consumption rises when third-party load is added. Both points are judgement calls for the CDC.
Property tax. $60,500 a year on an assumed $5.5 million real property assessed value at a 1.1 percent effective levy (MMCG assumption); Ada County's levy and the personal property treatment were not sourced.
Rentable Property and Occupancy Schedule
Measurement standard: BOMA 2018 Industrial, applied to an MMCG schematic plan because no floor plan is published; the areas are MMCG assumptions.
| Area | Square feet | Classification | Counted in Rentable Property |
|---|---|---|---|
| Data hall A (borrower) | 1,500 | Borrower | Yes |
| Data hall B (third-party cabinets) | 2,700 | Leased (conservative) | Yes |
| Electrical and switchgear room | 900 | Shared | Yes (Cases A and B); No (Case C) |
| UPS room | 700 | Shared | Yes (A and B); No (C) |
| Battery room | 400 | Shared | Yes (A and B); No (C) |
| NOC | 600 | Borrower | Yes |
| Office (MSP staff) | 3,000 | Borrower | Yes |
| Storage and staging | 900 | Borrower | Yes |
| Corridor | 1,100 | Common | Yes |
| Restrooms and break (common area) | 520 | Common | Yes |
| Mechanical (CRAH gallery, fire riser) | 700 | Mechanical | No |
| Telecom entrance room | 120 | Borrower | Yes |
| Stairway and elevator | 0 (single story, to confirm) | Excluded | No |
| Generator yard (exterior) | 1,200 | Shared, exterior operational | Yes |
| Cooling plant pad (exterior) | 900 | Shared, exterior operational | Yes |
| Parking | n/a | Excluded | No |
| Total interior | 13,140 | ||
| Rentable Property (Cases A and B) | 14,540 |
Test results at Year 5 under the 51 percent existing-building rule (SOP 50 10 8, Section A, Chapter 3, Paragraph C.1; 13 CFR 120.131). Case A counts only data hall B as leased, 2,700 square feet: borrower occupancy 81.4 percent, a 30.4-point margin. Case B counts hall B plus shared space allocated by the third-party share of contracted kW (340 of 540 kW, 63.0 percent): 5,281 square feet leased, occupancy 63.7 percent, a 12.7-point margin. Case C treats the electrical, UPS and battery rooms as mechanical, removing 2,000 square feet for a 12,540-square-foot denominator and allocating the exterior pads pro rata: occupancy 67.4 percent. Moving the electrical, UPS and cooling rooms between operational and mechanical swings the result by several points, and the classification is a judgement call for the lender.
Under the new-construction alternative's 60 percent test with 20 percent permanent and 20 percent temporary leasing, Case A puts third-party space at 18.6 percent of Rentable Property, inside the permanent allowance, but Case B puts it at 36.3 percent, which exceeds the permanent allowance and depends on temporary space the borrower would have to absorb within 3 and 10 years, not credible for a permanent colocation business. That is why the existing building is selected.
Trade Area Demographics
The trade area is the Treasure Valley, Ada and Canyon Counties, by latency. Census County Business Patterns establishment counts were not retrieved. MMCG's target list of regulated institutions, regional banks and credit unions, hospital systems, insurers, county and city government and school districts, is unverified as to demand and is carried as a condition. The demographic fact that matters is the borrower's own customer base of Treasure Valley small and medium businesses, which supplies the anchor load.
Demand and Penetration
Anchor load. The borrower's 200 kW contracted, 140 kW drawn, and $210,000 of monthly recurring managed hosting revenue are MMCG assumptions. Benchmarked at the incumbent's published $300 per kW per month, the same load costs $60,000 a month, $720,000 a year, to lease, which is the avoided cost that carries the global case.
Third-party demand. Published local evidence is supply-side: ValorC3 is building 10 MW at 9601 W Emerald and applied to nearly double it before opening. No demand-side kW figure for the valley was found, so the penetration test uses a supply proxy of about 7 MW, the sum of the incumbent's 1.4 MW, ValorC3 Boise 1's 1.15 MW critical and Centeris' 4.5 MW utility capacity.
Penetration test. Each Year 5 third-party kW contributes $2,764.80 a year of global cash flow after power and percentage costs. At zero third-party load, global cash flow after distributions is $1,217,702 against global debt service of $1,248,201.
| Coverage threshold | Third-party kW needed | Cabinets at 5 kW | Share of 400 kW third-party capacity | Share of about 7 MW identified Boise retail supply |
|---|---|---|---|---|
| Global 1.00x | 11 | 2 | 2.8 percent | 0.2 percent |
| Global 1.15x (lender floor) | 79 | 16 | 19.7 percent | 1.1 percent |
| Global 1.25x | 124 | 25 | 31.0 percent | 1.8 percent |
| Project NOI break-even | 177 | 35 | 44.3 percent | 2.5 percent |
| Project 1.00x | 559 | 112 | Not achievable | n/a |
Arithmetic for the 1.25x row: (1.25 × $1,248,201 less $1,217,702) ÷ $2,764.80 = 124 kW. At the 400 kW third-party design cap, the existing building stays at or above 62.6 percent borrower occupancy under Case B.
Competitive Supply
Rates are quoted only where an operator publishes them. All sites were accessed 4 October 2026.
Competitor Number 1 IDACORE Boise This facility is located at 2653 S Victory View Way, Boise, operated by IDACORE (Lincoln Freedom Group, LLC). It offers 1.4 MW of facility power in 34,000 square feet, N+1 UPS and cooling and 7 on-net carriers; cabinet count and density are not published. Its own website publishes $300 per kW per month on 12-month terms, with IP transit at $170 (100M), $600 (1G), $2,000 (10G) and $11,050 (100G); cross-connect pricing is not published. Its homepage also cites $125 per U per month, which conflicts with the per-kW billing statement, and the per-kW figure is used. A directory lists Ark Data Centers Boise 1 at the same address; the relationship is unverified. This is the facility the hypothetical borrower leaves.
Competitor Number 2 ValorC3 Boise 1 This facility is located at 10215 W Emerald Street, 1.15 MW critical load in 45,000 square feet, offering cabinets, cages and suites, with a 46 MW dedicated substation advertised. Rates not published.
Competitor Number 3 ValorC3 Boise 2 This facility is located at 9601 W Emerald Street, 38,000 square feet, 10 MW, valued above $20 million, approved by the City of Boise, with an expansion application filed March 2026 and the campus stated as coming in 2027. Announced and under-construction supply. Rates not published.
Competitor Number 4 Centeris / DataSite Boise This facility is located at 9700 W Bethel Court, 4.5 MW utility power expandable to 7 MW with 7.75 MW of diesel generation; the source is dated. Rates not published.
Competitor Number 5 Ark Data Centers Boise 2 (formerly Involta) This facility is located at 1450 S Eagle Flight Way, Tier III, offering third, half and full cabinets. Rates not published.
Competitor Number 6 Lumen Boise 1 This facility is located at 2223 W Airport Way. Rates not published.
Competitor Number 7 Syringa Networks This facility is located at 3795 Development Avenue. Rates not published.
Competitor Number 8 CenterServ and Synoptek Directory listings at 950 W Bannock Street and 412 E Parkcenter Boulevard. Rates not published.
Competitor Number 9 T5 Data Centers Nampa An approved industrial conversion at 8300 Birch Lane, planned.
Competitor Number 10 Meta Kuna A 120 MW hyperscale campus; not retail competition.
The nearest alternative markets are IDACORE North in Coeur d'Alene and IDACORE East in Eastern Oregon, which publishes $175 per kW plus utility pass-through on a 1 MW minimum for an AI product targeted at Q4 2026. Neither substitutes for low-latency Treasure Valley retail colocation. Boise has one operator-published rate card, not the two the selection criteria asked for, and that shortfall is carried as a condition.
Pricing and Rate Positioning
The subject's rate card is all-in with power to contracted kW: $250 per kW per month under 20 kW, $225 for 20 to 100 kW, $200 above 100 kW, a modeled blend of $230, which is $1,150 per 5 kW cabinet. Cross-connects are $150 per month, remote hands $150 per hour, IP transit resold at the incumbent's tiers, terms of 1 to 3 years with a 3 percent annual escalator, churn handled in the kW ramp plus a 2 percent credit loss. The blend sits 23 percent below the incumbent's $300, 21.5 percent below Digital Realty's Q2 2026 Americas achieved $293 for 0 to 1 MW, and inside CBRE's Q1 2026 Northern Virginia band of $190 to $235 for 250 to 500 kW. The discount is deliberate: customers must move from an established incumbent, pricing on contracted rather than drawn kW raises the effective rate per drawn kW by about 1.4x at 70 percent utilization, and no in-market second rate card supports parity.
The borrower's own 200 kW is carried at a shadow transfer price of $230 at the project level only and eliminated in the global cash flow, where the benefit is the avoided $720,000 of rent. Third-party revenue is the only revenue that counts as leased for the occupancy test and is classified as service revenue for the passive-business test.
Ramp and Occupancy
| Year | Third-party contracted kW | Borrower kW | Total contracted kW | Utilization of 600 kW | Occupancy, Case B (51 percent test) |
|---|---|---|---|---|---|
| Year 1 | 100 | 200 | 300 | 50 percent | 72.0 percent |
| Year 2 | 200 | 200 | 400 | 67 percent | 67.3 percent |
| Year 3 | 280 | 200 | 480 | 80 percent | 65.0 percent |
| Year 4 | 320 | 200 | 520 | 87 percent | 64.1 percent |
| Year 5 | 340 | 200 | 540 | 90 percent | 63.7 percent |
Closing is modeled in the first quarter of 2027 with a nine-month conversion and two months of overlapping rent at the incumbent during migration.
Project Cost Estimate
Location: 10051 W Emerald Street, Boise, ID 83704 Building: 13,140 square feet, existing | Critical IT load: 600 kW
| Item | Cost | Cost in % | Cost per kW |
|---|---|---|---|
| Land and Building | |||
| Acquisition at list price | $2,700,000 | 24.4% | $4,500 |
| Closing, title, survey, ALTA | $40,000 | 0.4% | $67 |
| Phase I ESA and geotechnical | $12,000 | 0.1% | $20 |
| Total Land and Building | $2,752,000 | 24.8% | $4,587 |
| Hard Cost | |||
| Demolition and structural and roof modification | $180,000 | 1.6% | $300 |
| Slab reinforcement | $60,000 | 0.5% | $100 |
| Site work, paving, equipment pads, screening | $150,000 | 1.4% | $250 |
| Electrical service upgrade and utility contribution (Rule H) | $250,000 | 2.3% | $417 |
| Switchgear, UPS, lithium-ion batteries, PDU, busway | $1,450,000 | 13.1% | $2,417 |
| Generators (2 × 1,000 kW, N+1), ATS, 24-hour fuel | $950,000 | 8.6% | $1,583 |
| Mechanical, containment, controls | $1,250,000 | 11.3% | $2,083 |
| Slab-mount with overhead cable tray | $60,000 | 0.5% | $100 |
| Fire detection and clean-agent suppression | $220,000 | 2.0% | $367 |
| Physical security and access control | $120,000 | 1.1% | $200 |
| Fiber entrance and laterals, two carriers | $180,000 | 1.6% | $300 |
| Rooftop solar, 120 kWdc | $270,000 | 2.4% | $450 |
| Interior build-out, office and NOC architectural | $200,000 | 1.8% | $333 |
| Commissioning, Levels 1 to 5 | $90,000 | 0.8% | $150 |
| Hard cost contingency (10%) | $543,000 | 4.9% | $905 |
| Total Hard Cost | $5,973,000 | 53.9% | $9,955 |
| Equipment | |||
| Cabinets and racks (120) | $216,000 | 1.9% | $360 |
| DCIM and BMS | $120,000 | 1.1% | $200 |
| NOC fit-out | $80,000 | 0.7% | $133 |
| Spare parts and tooling | $40,000 | 0.4% | $67 |
| Borrower servers and network gear (excluded from 504; funded by 7(a)) | $900,000 | 8.1% | $1,500 |
| Total Equipment | $1,356,000 | 12.2% | $2,260 |
| Financial Cost | |||
| 504 debenture fees (CDC processing, SBA upfront 0.5%, funding, underwriting; about 2.65%) | $90,062 | 0.8% | $150 |
| 504 ongoing SBA, CDC and CSA fees (carried in the effective rate) | $0 | 0.0% | $0 |
| Third-party lender fee (about 1.0%) | $47,000 | 0.4% | $78 |
| 7(a) guaranty fee | $42,500 | 0.4% | $71 |
| Appraisal (going-concern capable) | $15,000 | 0.1% | $25 |
| Feasibility study | $25,000 | 0.2% | $42 |
| Business valuation (not applicable; no change of ownership) | $0 | 0.0% | $0 |
| Builder's risk | $30,000 | 0.3% | $50 |
| Property tax during construction (9 months) | $20,250 | 0.2% | $34 |
| Interim construction interest | $313,000 | 2.8% | $522 |
| Working capital and ramp reserve | $417,500 | 3.8% | $696 |
| Total Financial Cost | $1,000,312 | 9.0% | $1,667 |
| Total Subject Project Cost | $11,081,312 | 100.0% | $18,469 |
Source: Marshall & Swift CoreLogic, MMCG
The 7(a) guaranty fee is 3.5 percent of the first $1,000,000 guaranteed plus 3.75 percent of the $200,000 above it, on a 75 percent guaranty of $1,600,000, at the FY2026 schedule. Interim interest is 90 percent of an average balance of $5.8 million at 8.0 percent for 9 months. The ramp reserve is the Year 1 shortfall to a global 1.25x ($284,498) plus two months of overlapping incumbent rent during migration ($120,000), rounded to $417,500.
Excluding the borrower's servers, the reserve and the 7(a) fee, facility all-in cost is about $9.72 million, or $16.2 million per MW, below Cushman & Wakefield's $17.6 million per MW greenfield all-in (3 September 2026; range $8.9 million to $23.3 million) because an existing shell replaces land and ground-up construction. Hard cost plus facility equipment is about $10.7 per watt, against Turner & Townsend's 2025 air-cooled figures of $10.9 for Portland and $9.8 for Phoenix and Columbus; Turner & Townsend does not list Boise and measures larger new builds. No published 2026 edge benchmark exists, so the build-up is project-specific.
Asset-Life Allocation
Basis: SOP 50 10 8, Section A, Chapter 3, Paragraph A.1; 504 fixed assets need a useful life of at least 10 years.
| Line | Useful life (MMCG) | 504 debenture project | 7(a) tranche | Working capital |
|---|---|---|---|---|
| Land, building, closing, ESA | 39 years / n.a. | $2,752,000 | ||
| Structural, slab, site work | 20 to 39 years | $390,000 | ||
| Electrical service, switchgear, busway, PDU; UPS and lithium-ion batteries | 20 to 30 years; 10 to 15 years (VRLA would move about $180,000 to 7(a)) | $1,700,000 | ||
| Generators, ATS, fuel | 20 to 25 years | $950,000 | ||
| Mechanical, controls, containment | 15 to 20 years | $1,250,000 | ||
| Fire, security, fiber, slab-mount | 10 to 25 years | $580,000 | ||
| Solar | 25 years | $270,000 | ||
| Interior build-out, commissioning, contingency | Follows assets | $833,000 | ||
| Cabinets | 15 years | $216,000 | ||
| Soft costs and interim interest (capitalized) | Follows assets | $450,250 | ||
| DCIM and BMS | 5 to 7 years | $120,000 | ||
| NOC fit-out | 7 years | $80,000 | ||
| Spare parts and tooling | 3 to 5 years | $40,000 | ||
| Borrower servers and network | 3 to 5 years | $900,000 | ||
| 7(a) guaranty fee | n.a. | $42,500 | ||
| Ramp reserve | n.a. | $417,500 | ||
| Totals | $9,391,250 plus $90,062 of debenture fees | $1,182,500 | $417,500 |
Loan Assumptions
| Item | As proposed | As restructured |
|---|---|---|
| 504 project | $9,391,250 | $9,391,250 |
| Third-party first lien (50%) | $4,695,625 | $4,695,625 |
| CDC debenture, net (40% / 35%) | $3,756,500 | $3,286,938 |
| CDC debenture, gross with fees | $3,859,000 | $3,377,000 |
| Borrower injection (10% / 15%) | $939,125 | $1,408,688 |
| 7(a) companion | $1,600,000 | $1,600,000 |
| Debenture rate | 6.54% effective, 25 years (SomerCor, 10 September 2026 pricing including CDC, SBA and CSA servicing fees; underlying 5.41% over a 4.91% Treasury per Growth Corp; next pricing 8 October 2026) | Same |
| First lien | 7.25% fixed, 10-year term, 25-year amortization (MMCG assumption; the bank term must be at least 10 years alongside a 25-year debenture) | Same |
| 7(a) | Prime plus 2.75% = 9.75% variable (WSJ prime 7.00% following the FOMC's 16 September 2026 move); 7-year term set by weighted useful life; program maximum base plus 3.0% on loans over $350,000 | Same |
| Annual debt service | First lien $407,287; debenture $274,632; 7(a) $316,282; new debt $998,201 | Same |
| Global debt service | $1,248,201 including $250,000 of existing operating company debt (MMCG assumption) | Same |
The restructured total exceeds uses by $1 on debenture rounding. The 10 percent tier applies in the proposal because the borrower is not a new business and MMCG's judgement is that the property is not special purpose; the 15 percent tier applies in the restructured case if the CDC, lender or appraiser treats the improved property as limited-market. The 20 percent tier does not apply because the business is not new. The injection source is operating company balance-sheet liquidity (MMCG assumption).
SBA Program Compliance
| Item | Citation | Verdict |
|---|---|---|
| Operator versus landlord (judgement call; confirm with the lender) | SOP 50 10 8, Section A, Chapter 1, Paragraph E.3; 13 CFR 120.110(c) | The borrower is an operating MSP. Third-party colocation is about 9 percent of combined revenue ($1.22 million of about $13.2 million in Year 5). Revenue lines classified as service: power, cooling, connectivity, cross-connects, remote hands, managed services. Colocation customers have assigned cabinets, which fails the E.3.i no-assigned-space prong if read as space rental, and E.3.ii bars mixed models. Proposed treatment: service revenue for the passive test, leased space for the occupancy test. |
| Eligible Passive Company | Section A, Chapter 2, Paragraph A; 13 CFR 120.111 | EPC holds the real estate: 100 percent lease to the operating company; lease term at least 25 years; rent capped at debt service plus direct holding costs; operating company co-borrower; every 20 percent owner guarantees. Passes as structured. |
| Occupancy | Section A, Chapter 3, Paragraph C.1; 13 CFR 120.131 | Existing building, 51 percent test: 63.7 to 81.4 percent, minimum margin 12.7 points. Passes. The new-build alternative fails under Case B. |
| Size | 13 CFR 121.201; 121.301 | $12.0 million against $40.0 million for 518210 (and $34.0 million for the 541512 fallback). Passes. The alternative standard passes on assumed tangible net worth of $3.5 million and net income of $0.9 million. |
| Special purpose property (judgement call; confirm with the CDC) | CRS R41184; CDC practice | A 2005 flex shell whose specialized items are removable equipment; MMCG estimates conversion back to flex at $150,000 to $250,000; data centers are absent from published CDC example lists. Proposed: not special purpose (10 percent). Restructured for underwriting: 15 percent. |
| Job opportunity test | 90 FR 47117 | About 5 jobs (4.5 facility FTE). Required: 36 at $95,000 or 23 at $150,000. Fails on jobs alone. |
| Public policy route | 13 CFR 120.862(b)(11), (b)(13) | 15.6 percent modeled reduction against a 1.54 baseline. Passes, conditional on engineer certification and on the CDC maintaining its portfolio job average. |
| Debenture cap | 13 CFR 120.931 | $5.5 million energy cap; $3.377 million is not binding. |
| Asset life | Section A, Chapter 3, Paragraph A.1 | Short-life items sit in the 7(a). Passes. |
| Combined limit | Policy Notice 5000-879058 | $4.977 million of SBA debt against $10 million; 7(a) guaranteed portion $1.2 million against $3.75 million. Passes. Close the 7(a) first if the combined-limit pathway is relied on. |
| SOP version | Information Notices 5000-880695 and 5000-882227 | Loan numbers on or after 1 October 2026 fall under SOP 50 10 8.1. |
| DSCR floor | Secondary summaries of 8.1 | 1.15x for business expansion. Secondary; confirm against the redline. |
Operating Expenses
Stabilized Year 5 at 540 kW contracted (378 kW drawn) and 108 cabinets. Facility payroll: facility manager 1.0, critical facilities technicians 2.0, NOC operator 1.0 (allocated), sales 0.5; benefits at 28 percent.
| Line (Year 5) | Amount | Per kW per month (540 kW) | Per cabinet per year (108) |
|---|---|---|---|
| Property tax (MMCG assumption) | $68,094 | $10.51 | $631 |
| Property, liability and cyber insurance | $57,401 | $8.86 | $531 |
| Payroll and benefits (4.5 FTE) | $557,537 | $86.04 | $5,162 |
| Purchased power, Schedule 9, PUE 1.35, gross | $362,730 | $55.98 | $3,359 |
| Solar offset credit | ($9,150) | ($1.41) | ($85) |
| Water and sewer | $6,753 | $1.04 | $63 |
| Electrical, mechanical, generator and UPS maintenance contracts | $101,296 | $15.63 | $938 |
| Repairs | $28,138 | $4.34 | $261 |
| Janitorial and security | $30,389 | $4.69 | $281 |
| Network transport and carrier fees | $54,024 | $8.34 | $500 |
| DCIM and software | $20,259 | $3.13 | $188 |
| Administrative and marketing | $61,898 | $9.55 | $573 |
| Sales commissions (3%) and card processing (1%) | $48,685 | $7.51 | $451 |
| 504 ongoing guaranty and CDC servicing | In the debenture rate | ||
| Management fee | None, owner-operated | ||
| Total operating expenses | $1,388,054 | $214.21 | $12,852 |
| Project revenue (third-party $1,217,122 plus internal transfer $621,281) | $1,838,403 | ||
| Net operating income | $450,349 | ||
| NOI margin | 24.5 percent | ||
| Lifecycle reserve ($8 per kW per month on 600 kW; low end of KBRA's $7 to $18 for new equipment) | $57,600 | ||
| Cash flow available for debt service | $392,749 |
The margin sits below the retail colocation range of 40 to 50 percent because a 24-hour staffing floor is spread over 600 kW, so payroll alone is 30 percent of revenue, and because the internal transfer is priced 23 percent below the incumbent. Power and property tax are within normal ranges.
Global cash flow. Lender sizing uses global cash flow, which in Year 5 is $2,607,750 before distributions: operating company EBITDA of $2,025,916, plus avoided incumbent rent of $810,366, less the facility's third-party net shortfall of $228,532.
Five-Year Pro Forma and Debt Service Coverage
Project level, with 3 percent escalation.
| Line | Year 1 | Year 2 | Year 3 | Year 4 | Year 5 |
|---|---|---|---|---|---|
| Third-party contracted kW | 100 | 200 | 280 | 320 | 340 |
| Third-party net revenue | $321,989 | $661,181 | $950,469 | $1,115,449 | $1,217,122 |
| Internal transfer (borrower 200 kW) | $552,000 | $568,560 | $585,617 | $603,186 | $621,281 |
| Total project revenue | $873,989 | $1,229,741 | $1,536,086 | $1,718,635 | $1,838,403 |
| Operating expenses | $1,058,636 | $1,165,323 | $1,261,989 | $1,331,659 | $1,388,054 |
| Net operating income | ($184,647) | $64,418 | $274,097 | $386,976 | $450,349 |
| Lifecycle reserve | $57,600 | $57,600 | $57,600 | $57,600 | $57,600 |
| Project cash flow available for debt service | ($242,247) | $6,818 | $216,497 | $329,376 | $392,749 |
| New debt service | $998,201 | $998,201 | $998,201 | $998,201 | $998,201 |
| Project DSCR | (0.24x) | 0.01x | 0.22x | 0.33x | 0.39x |
Global level.
| Line | Year 1 | Year 2 | Year 3 | Year 4 | Year 5 |
|---|---|---|---|---|---|
| Operating company EBITDA (status quo, MMCG assumption) | $1,800,000 | $1,854,000 | $1,909,620 | $1,966,909 | $2,025,916 |
| Avoided incumbent rent | $720,000 | $741,600 | $763,848 | $786,763 | $810,366 |
| Facility third-party contribution after reserve | ($794,247) | ($561,742) | ($369,120) | ($273,810) | ($228,532) |
| Global cash flow before distributions | $1,725,753 | $2,033,858 | $2,304,348 | $2,479,862 | $2,607,750 |
| Owner distributions (MMCG assumption) | $450,000 | $450,000 | $450,000 | $450,000 | $450,000 |
| Global debt service | $1,248,201 | $1,248,201 | $1,248,201 | $1,248,201 | $1,248,201 |
| Global DSCR after distributions | 1.02x | 1.27x | 1.49x | 1.63x | 1.73x |
| Global DSCR with distributions added back | 1.38x | 1.63x | 1.85x | 1.99x | 2.09x |
| Occupancy, Case B (51 percent test) | 72.0% | 67.3% | 65.0% | 64.1% | 63.7% |
| Third-party share of Rentable Property, Case B | 28.0% | 32.7% | 35.0% | 35.9% | 36.3% |
Year 1 sits below the 1.15x floor; the shortfall of $159,678 is covered by the $417,500 ramp reserve.
Break-Even Analysis
Year 5 basis, third-party kW against the 400 kW third-party capacity.
| Threshold | Third-party kW | Third-party utilization |
|---|---|---|
| Project NOI break-even | 177 | 44 percent |
| Global 1.00x | 11 | 3 percent |
| Global 1.15x (lender floor) | 79 | 20 percent |
| Global 1.25x | 124 | 31 percent |
| Project 1.00x | 559 | Not achievable |
The global floor clears at 20 percent third-party utilization against a 85 percent forecast. The project-level 1.00x threshold exceeds the facility's third-party capacity, which is the credit fact: the building is a cost center for the MSP that becomes cheaper than leasing, not a data center that pays for itself.
Sensitivity Analysis
Year 5 global DSCR after distributions; base case 1.73x.
| Case | Result |
|---|---|
| Rent per kW 10 percent below forecast | 1.64x |
| Third-party utilization 10 points low (300 kW) | 1.64x |
| Third-party utilization 20 points low (260 kW) | 1.55x |
| Power cost 20 percent above forecast | 1.67x |
| PUE 1.6 | 1.67x; the energy reduction turns negative against the 1.54 baseline, so the (b)(11) route fails and the 504 needs a (b)(13) renewable showing or fails |
| Solar output 15 percent below estimate | 1.73x; energy reduction 15.1 percent, still passes |
| Construction cost 15 percent over (+$895,950; debenture about $3.70 million) | 1.64x |
| Debenture rate +100 basis points (7.54 percent) | 1.69x |
| Third-party area exceeds the allowance (3,000 square feet of office converted to third-party hall) | Occupancy 42.0 percent; ineligible, restructure required |
| Loss of the three largest MSP customers (25 percent of revenue, $1.05 million of EBITDA) | 0.89x; 1.00x if the freed 50 kW is resold; fails the floor |
| Make versus buy: stay at the incumbent at $300 per kW per month | Status quo free cash after debt service $1,325,916, against $909,549 with the project; building costs $416,367 of Year 5 cash, roughly offset by about $419,000 of principal amortization in the new debt |
The project is insensitive to its own revenue and sensitive to the operating company's. Loss of the top three customers is the case that breaks it, which is why customer concentration is a condition.
Risk Factors and Mitigants
- Energy baseline. The (b)(11) route rests on an industry-average PUE, not the incumbent's metered figure, and fails at a design PUE of 1.6. Mitigant: an engineer-stamped baseline from metered consumption and a contractual design PUE of 1.35 or better.
- Customer concentration. The global case fails if the top three MSP customers leave. Mitigant: concentration evidence below 15 percent as a condition; if higher, staying at the incumbent is the better decision.
- Space-rental classification. Assigned cabinets conflict with the E.3.i prong. Mitigant: service-fee contracts, operator-owned critical infrastructure and bundled power and connectivity documented in the file; lender determination before closing.
- Special purpose. Mitigant: underwrite at 15 percent and obtain a written CDC determination.
- Occupancy drift. Converting office to a third-party hall drops occupancy to 42 percent. Mitigant: a covenant capping third-party space at data hall B and keeping the office borrower-occupied.
- Building unknowns. Service capacity, slab, roof and vacant delivery are unverified. Mitigant: an Idaho Power load letter for about 1 MW, a Planning Director use interpretation and the assessor record before the LOI.
- Variable 7(a) rate. Mitigant: the 7-year term limits exposure; a 100 basis point move costs 4 points of coverage.
Conditions and Limitations
The determination of feasible as restructured is subject to the following conditions precedent:
- An engineer-stamped energy baseline using the actual metered PUE at the incumbent facility, and a contractual design PUE of 1.35 or better, supporting the 13 CFR 120.862(b)(11) showing.
- Customer-concentration evidence that the borrower's top three customers are below 15 percent of revenue.
- A written CDC determination on special purpose status, with the injection set at 15 percent.
- A loan covenant capping third-party space at data hall B and keeping the office borrower-occupied.
- Before LOI: the listing ID, zoning verification, assessor record, electrical service capacity, vacant-delivery terms, a Planning Director use interpretation and an Idaho Power load letter for about 1 MW.
- The SBA FOIA NAICS 518210 screen run before the CDC presents the deal as precedent-free.
The following items could not be verified from a primary source at the study date and are disclosed: the subject's listing ID, days on market, acreage, zoning district, Ada County parcel, power service, slab, clear height, column spacing, roof and HVAC; data center use, generator noise limits, screening and solar permitting under Boise Title 11; the I-1 hazardous-substance limit as applied to diesel and batteries; whether the Suite 120 tenant vacates; the Rentable Property schedule, which is a schematic MMCG plan; the absence of a second operator-published rate card in Boise; the conflict between the incumbent's per-U and per-kW statements and its relationship to the Ark facility; competitor capacities from dated directories; County Business Patterns and named-institution demand; the PVWatts run, the solar yield and the $2.25 per watt cost; Idaho Power's 2026-27 export credit update, Schedule 20 applicability and rider percentages (the current export credit rates are 15.6836 cents summer on-peak, 3.3920 cents summer off-peak and 2.9019 cents non-summer under Order No. 36785, covering 1 June 2025 to 31 May 2026); the 1.54 PUE baseline as an industry average; the 15 percent renewable-generation threshold some practitioners cite, not used; the FY2026 504 upfront guaranty fee of 0.50 percent, up from 0 percent in FY2025 per the Northwest Business Development Association; all SOP 50 10 8.1 content changes including DSCR floors; the borrower's revenue, headcount, EBITDA, distributions, existing debt, tangible net worth and customer concentration, which are MMCG assumptions without a sourced industry benchmark; Ada County's levy and personal property treatment; and federal energy credit treatment, which is for the borrower's tax counsel.
Judgement calls: the colocation space-rental classification, the special purpose determination, the energy-baseline comparator and the shared-space occupancy classification. Each must be confirmed with the lender and CDC.
What the Lender Received
- The written determination with the as-proposed and restructured capital stacks stated side by side and six conditions precedent
- The metro screen and the subject selection rationale, with the new-build alternative priced and rejected on the 60 percent test
- The Rentable Property schedule under three classification cases with the margin under each
- The energy baseline model for the 120.862(b)(11) showing, with its comparator disclosed as an industry average
- The competitor census with the one published rate card quoted from the operator's own website and the unpublished facilities named
- The rate card, the transfer-price treatment of the borrower's own load and the ramp to 540 kW
- The project cost estimate in MMCG's standard format with the asset-life allocation between the debenture, the 7(a) and working capital
- The sources and uses, the debenture pricing with its date, and the SBA compliance matrix
- The operating budget by line, the project pro forma and the global cash flow with DSCR three ways
- Break-even at each threshold and the sensitivity cases, including the make-versus-buy comparison against the incumbent's published rate
This model study applies the methodology described on MMCG's Data Center Feasibility Study and SBA Data Center Feasibility Study pages. MMCG prepares data center feasibility studies for SBA 7(a) and 504, USDA Business and Industry and REAP, and conventional lenders nationwide, with engagements from $4,900 and delivery in 9 to 16 business days.
Sources
- LoopNet, 10051 W Emerald Street, Boise, ID 83704, TOK Commercial; CityFeet broker listing; LoopNet, 1471 S Eagle Flight Way, Boise; accessed 4 October 2026
- IDACORE, Boise facility page and homepage, rates and transit pricing, accessed 4 October 2026
- ValorC3 Data Centers, Boise one-pager (April 2026) and LinkedIn; BoiseDev, Boise data center set to open next year, 26 March 2026
- Datacentermap, Datacenters.com, Cloud and Colocation, Baxtel and Inflect directory listings for Boise, Sioux Falls and Spokane facilities, accessed 4 October 2026
- Idaho Power, Schedule 9 Large General Service and Schedule 19 Large Power Service tariff sheets, effective 1 January 2026; Rule H line extension tariff; Schedule 84 net billing; Retail Tariffs in Idaho index
- Idaho Public Utilities Commission, Order No. 36785, 30 September 2025
- City of Boise, Industrial Light zoning district page; Boise Zoning Code Section 11-03-01 and Table 11-03.1; Zoning Ordinance Module 1 and 2 revised public draft; Emerald Flex Building marketing flyer (M-1D)
- Yelp listing, 10051 W Emerald Street, Suite 120, updated July 2026
- SomerCor, September 2026 SBA 504 interest rates, 10 September 2026; Growth Corp, SBA 504 rate pricing
- Bankrate, current SBA loan rates, updated 29 September 2026; NAGGL, FY2026 loan fees; SBA 7(a) rate and fee calculator
- U.S. Small Business Administration, SOP 50 10 8, Section A, Chapter 1, Paragraphs D.1, E.3 and E.18; Chapter 2, Paragraph A; Chapter 3, Paragraphs A.1 and C.1, effective 1 June 2025
- U.S. Small Business Administration, Information Notice 5000-880695, 14 August 2026, and Information Notice 5000-882227, 25 September 2026; Policy Notice 5000-879058, 18 May 2026
- 13 CFR 120.110, 120.111, 120.131, 120.862, 120.931, 121.201 and 121.301
- Federal Register, 90 FR 47117, 30 September 2025
- Congressional Research Service, R41184, Small Business Administration 504/CDC Loan Guaranty Program
- Eastern Idaho Development Corporation; Frontier Community Resources CEDS appendix; Northwest Business Development Association; WaFd Bank SBA lending page
- Digital Realty, Second Quarter 2026 Results, 23 July 2026; CBRE, Global Data Center Trends 2026 (Q1 2026) and North America Data Center Trends H1 2026
- Cushman & Wakefield, 2026 Data Center Development Cost Guide, 3 September 2026; Turner & Townsend, Data Centre Construction Cost Index 2025 to 2026, November 2025
- Uptime Institute, Global Data Center Survey 2025; KBRA presale, DataBank 2026-1, 12 January 2026; CRE Finance Council, Data Center E-Primer, 25 February 2026
- U.S. Energy Information Administration, Electric Power Monthly, April 2026 data
- Marshall & Swift CoreLogic, cost data, 2026
